Lemay Pump Station
AFRAM, as a sub-consultant, prepared the preliminary concept schedule and resource-loaded design schedule for two options at the Lemay Wastewater Treatment Pump Station.
01 Project summary
- Construction Cost: Option 1: $3,900,000; Option 2: $2,500,000
- Project Fee: $69,391
- Final Design Time: Nine (9) months
AFRAM, as a sub-consultant, prepared the preliminary concept schedule and resource-loaded design schedule for two options at the Lemay Wastewater Treatment Pump Station. Monthly updated design schedules were developed to track design progress and maintain milestone dates. AFRAM prepared conceptual budgets and design-build/cost estimates, along with life cycle cost analyses for both pump station options. Additionally, AFRAM contributed to design review efforts, implementing value engineering methods to identify cost reduction opportunities.
From the Stormwater & Sewer Experience Work Sheet in ACOT’s capability statement (AFRAM Corporation).
02 More projects
Related experience.
Coldwater Creek Treatment Plant
AFRAM Corporation was part of the team led by Black & Veatch Corporation on the Coldwater Treatment Plant Improvements located at 13798 Old Halls Ferry Road in North St.
Creve Coeur Pump Station L-52
AFRAM was part of the team with URS to provide construction management services for the construction of a new 60 MGD capacity wastewater pump station.
Grand Glaize Wastewater Treatment Plant
This project consists of the expansion of an existing WWTP to provide odor control and process increasing quantities of wet weather flow.